Cain Industries – Germantown, WI
Cain Industries’ original building was constructed in 1998, and subsequent expansion was required in 2007.
Dave’s Electric was integrally involved in the design process for the new building in 1998. We spent considerable time meeting with the owner to determine the needs for the building and subsequent equipment installation.
Many of the required feeder conduits for the machines were able to be installed under the concrete to precise locations with advanced planning. This saved Cain Industries considerable time and money when the machines were moved to the new facility. The 2007 building addition was very similar with the additional challenge of matching existing finishes.